AUBURN, Calf. June 20, 2024 – Placer County Water Agency (PCWA) Directors and members of the public received a status update on the ongoing repairs at the Spaulding facilities from Eric Van Deuren, Sr. Director Power Generation Project Execution for PG&E. His report contained new information, including the root cause for the failed discharge horns […]
spaulding
Spaulding SNAFU prompts irrigation water outages, NID and PCWA to consider additional actions
Grass Valley Calif. June 13, 2024 – Yesterday’s Nevada Irrigation District (NID) Board of Directors meeting was overshadowed by yet another announce of a significant delay in repair completion at PG&E’s Spaulding facilities. Directors had very pointed questions for the utility’s representative, but few answers were forthcoming. Due to the ever-changing return to service dates […]
PG&E Repair Delays Worsen Water Delivery Challenges: PCWA and NID Respond
Auburn and Grass Valley, Calif. (June 13, 2024) — The Placer County Water Agency (PCWA) and Nevada Irrigation District (NID) have issued the following statement in response to the Pacific Gas & Electric (PG&E) company’s recent announcement regarding further delays in repairing essential water delivery infrastructure at their Spaulding #1 Powerhouse. Initially scheduled for completion […]
Spaulding powerhouse repair completion date slips to late July
GRASS VALLEY, Calif. June 12, 2024 – Less than two weeks ago, PG&E notified Nevada Irrigation District (NID) and Placer County Water Agency (PCWA) that the expected completion date for repairs at the Spaulding #1 Powerhouse was once again extended, this time from June 19 to June 30. Today, that date was pushed to late […]
Rotating canal outages due to Spaulding repair delays
GRASS VALLEY, Calif. June 10, 2024 – Nevada Irrigation District (NID) Directors will vote on establishing Emergency Canal Outage Rotations throughout the duration of the PG&E’s unplanned Spaulding One and South Yuba Canal outages at their June 12th meeting. Why the outages? The initial return to service date of the Spaulding #1 Powerhouse was scheduled […]
Delays in PG&E’s Spaulding Powerhouse #1 repairs extend completion date to June 30
The repairs at PG&E’s Spaulding Powerhouse #1 have been delayed until June 30th due to the need for more time for the steel discharge tube liner installation.
Spaulding powerhouse repairs on track, South Yuba Pipe repair delayed
PG&E is working to repair the South Yuba Pipe by late August, Powerhouse #1 repairs are on track to be completed by mid-June, providing half the powerhouse flow capacity through the irrigation season.
PG&E answers to NID Board question re Spaulding
GRASS VALLEY, Calif. May 8, 2024 – NID updated their webpage listing their Directors’ questions to PG&E at their last board meeting with answers provided by the utility corporation. A new development appears to be the permanent repair only on the South Yuba pipe, damaged by a rockslide in early February. “PG&E is no longer […]
PG&E workshop during NID meeting – many questions, few answers
GRASS VALLEY, Calif. April 25, 2024 – During Wednesday’s NID Board meeting, a workshop item was on the agenda to update the Board and the public on the various infrastructure issues at PG&E’s Spaulding powerhouses and pipes/canals. Four separate issues have been reported, cutting off water flow to NID and PCWA systems. PG&E’s government liaison […]
PG&E repairs to South Yuba pipe below Spaulding – update
NEVADA COUNTY, Calif. April 23, 2024 – PG&E appears to be working on a temporary repair of the damaged pipe section of the South Yuba Pipe and implement a permanent fix once “pipe is procured for those long‐term repairs,” according to a document filed by the State Historic Preservation Officer (SHPO) with the Federal Energy […]
Spaulding update: One of four issues restored to half capacity by mid-June
NEVADA COUNTY, Calif. April 18, 2024 – The latest update from PG&E on the infrastructure issues at Spaulding powerhouse #1 and assorted pipes reads as follows: PG&E is proceeding with repairs to the first discharge horn and structural column so that water can begin flowing through the Spaulding 1 powerhouse as early as June 12. […]
South Yuba Pipe damage – video and photos
NEVADA CiTY, Calif. April 10, 2024 – In early February, a rockslide during a severe winter storm took out a portion of the South Yuba Pipe, the PG&E-owned portion of the South Yuba Canal right below Spaulding Reservoir. Today, we ventured on Bowman Lake Road to bring you photos and video of the damage. There […]
Spaulding outages and their preliminary effects
PG&E’s ongoing twin outages of its Spaulding powerhouse #1 and South Yuba Pipe are forecast to have major impacts on water deliveries and the Bear River/Drum systems, with NID and PCWA coordinating efforts to ensure water for their customers.
PG&E updates outlook for Spaulding powerhouse repairs
Nevada County Calif. April 4, 2024 – In response to a query from YubaNet, PG&E spokesperson Paul Moreno provided an update on the progress of repairs at the Spaulding 1 powerhouse. The first deadline for restoration was April 30th, followed by a June 8th repair completion estimate after a closer inspection of the damage. Yesterday, […]
Details on Spaulding powerhouse damages emerge
NEVADA COUNTY, Calif. April 3, 2024 – Two letters filed with the Federal Energy Regulatory Commission (FERC) reveal details of the damage at PG&E’s Lake Spaulding Powerhouse No. 1, which is out of service since early March. The failure of the powerhouse, combined with a massive rockslide over the PG&E-owned starting portion of the South […]
FERC notified PG&E in August of issue at Spaulding powerhouse
NEVADA CITY, Calif. March 25, 2024 – The outage at PG&E’s Spaulding #1 powerhouse, first reported by us on March 9th, was described by PG&E as follows: “During a routine inspection at PG&E’s Spaulding 1 powerhouse on March 6, a leak was discovered adjacent to a pressure relief valve.” A search of public documents on […]
Lake Spaulding powerhouse #1 offline after leak discovered
NEVADA COUNTY, Calif. March 9, 2024 – NID released a notice informing the public of cuts to the Bear River water flows yesterday afternoon. The district cited “unexpected maintenance work in the headwaters” in their release. We can now confirm a shutdown of PG&E’s Spaulding #1 powerhouse is the cause of what could be a […]