PLACER COUNTY – Caltrans is reminding motorists of various lane closures in multiple locations along State Route 49 (SR 49) as several improvement projects continue in Placer County. 

Here is the breakdown for the week:

American River Canyon Roundabout Project

  • SR 49 remains closed between the intersection with Lincoln Way/Borland Avenue and the American River Confluence. Motorists traveling between Auburn and Cool will detour using Foresthill Road and Old Foresthill Road. SR 49 is scheduled to reopen in the new roundabout configuration by 6 a.m. Monday, December 22.
Hwy 49 roundabout work

Sidewalk Gap Closure Project

  • Southbound between Dry Creek Road and Bell Road, various lane closures are scheduled for drainage work from 7 p.m. to 7 a.m. Sunday, December 14 through Thursday, December 18. Work is scheduled to end for the week by 7 a.m. Friday, December 19.
  • Southbound between Luther Road and Edgewood Road, various lane closures are scheduled for utility work from 10 p.m. Sunday, December 14 to 6:30 a.m. Monday, December 15 and from 8 p.m. to 6:30 a.m. Monday, December 15 through Thursday, December 18. Work is scheduled to end for the week by 6:30 a.m. Friday, December 19.
State Route 49 Construction Update for Gold Country Corridor

The extended lane closures will help to minimize the duration of the work and improve workers’ safety. Motorists may experience delays between 15 to 20 minutes, depending on traffic volumes. The schedule is subject to change or be delayed due to weather, availability of materials or other unexpected events. 

Caltrans District 3 is responsible for maintaining and operating 4,385 lane miles in 11 Sacramento Valley and Northern Sierra counties. Caltrans reminds motorists to “Be Work Zone Alert” and slow in construction zones for the safety of travelers and crews performing these improvements.